Home/Projects

References

34 completed reference projects — and over 650 MW under construction.

Substations and switching stations up to 400 kV, overhead and cable lines, battery parks from 10 to 150 MW, photovoltaic plants, industrial buildings — for ESO EAD, the distribution companies and leading renewable investors.

11battery parks (BESS)
10substations and switchgear
8overhead and cable lines
5PV, buildings and LV networks

Key projects

The projects that define who we are.

Complex turnkey energy facilities — from design to energisation.

Substations · 400 kV“Tenevo Solar” PV — a complex energy project

2024 – 2025 · Tenevo · Solarpro Technology AD

“Tenevo Solar” PV — a complex energy project

Supply and construction across three sub-projects: an MV/400 kV substation with a cable duct, a 400 kV switching station connecting a generation, storage and consumption facility, and reconstruction of the “San Stefano” 400 kV line. Main contractor. 400 kV

BESS · 110 kVBurgas Energy Complex — our largest completed battery park

2025 – 2026 · Burgas · Solarpro Technology AD

Burgas Energy Complex — our largest completed battery park

A 150 MW / 601.70 MWh battery system, a 110/20 kV step-up substation and a 110 kV cable line with fibre-optic cable to the “Burgas” 400/110/31.5/20 kV substation, Balgarovo. Main contractor. 150 MW / 601.7 MWh

Substations · OHL · BESSSmolyan Energy Complex — “Rozhen” substation and BESS 320 MWh

from 12.2024 · Smolyan · Smolyan – VE EAD

Smolyan Energy Complex — “Rozhen” substation and BESS 320 MWh

A new “Rozhen” 20/110 kV substation, a new “Rozhen” 110 kV line with OPGW / OPUG to the “Smolyan” 110/20 kV substation, a new 110 kV bay and switchyard reconstruction, a 320 MWh battery system — on mountain terrain and to a tight schedule. Turnkey main contractor. 320 MWh

BESS · hybrid with wind“Vetrokom” battery storage

12.2024 – 04.2025 · Solarpro Technology AD

“Vetrokom” battery storage

BESS 65.55 MW / 154.77 MWh connected to the operating energy facility of Vetrokom EOOD — integrating storage with a running wind farm without interrupting generation. 65.55 MW / 154.77 MWh

Substations · 110 kVTwo new 33/110 kV substations — “Kameno” and “Brusartsi”

2025 · Kameno and Brusartsi · Sunotec

Two new 33/110 kV substations — “Kameno” and “Brusartsi”

Design and construction of two 33/110 kV step-up substations with equipment supply, an external 110 kV cable connection and new line bays in ESO’s “Kameno” and “Brusartsi” substations — in partnership with Futura Systems EOOD. 2 × 33/110 kV

BESS · seriesA series of standardised 10 MW / 40 MWh battery parks

03 – 08.2026 · 7 sites

A series of standardised 10 MW / 40 MWh battery parks

Kaliakra, Kavarna, Trastikovo 1 and 2, Staro Oryahovo, Dalgopol Storage Park and Energy Park — one technical design for fast, repeatable delivery, with a new 20 kV cable line and fibre-optic cable. All commissioned in August 2026. 7 × 10 MW / 40 MWh = 70 MW / 280 MWh

BESS · own foundations“Tenevo” battery parks — stages 1, 2 and 3

2025 – 2026 · Tenevo · Solarpro Technology AD

“Tenevo” battery parks — stages 1, 2 and 3

Stage 1 — 60 MW / 240 MWh; stages 2 and 3 (50 MW / 200 MWh and 75 MW / 300 MWh) under construction. Like all our battery parks — on foundations of our own production. Together, over 185 MW / 740 MWh of new capacity next to “Tenevo Solar”. > 185 MW / 740 MWh

PV + BESS · rooftopRooftop PV 1,132 kWp with a 2,120 kWh battery

3 months · Plovdiv · Krasin OOD

Rooftop PV 1,132 kWp with a 2,120 kWh battery

Design, supply and construction of a rooftop PV system with battery storage on an industrial building on Kuklensko Shose St. — self-generation and consumption optimised through local storage. 1,132 kWp / 2,120 kWh

ESO EAD · modernisationModernising the transmission grid — partnership with ESO EAD

2020 – 2026 · 6 substations

Modernising the transmission grid — partnership with ESO EAD

110 kV switchyards at “Iskar Industria”, “Aldomirovtsi”, “Zlatograd”; 20 kV bays at “Hristo Smirnenski”; a new control building at Plovdiv CHP; “Stolnik” and “Trakia” — from dismantling worn equipment through new steel structures and earthing to installation and energisation, without compromising grid reliability. 110 – 220 kV

Under construction

Over 650 MW of new capacity — right now.

New large projects in Bulgaria and Romania, including full design-and-build scope.

Gabare · Bulgaria · Sunotec

Grid connection of the “Gabare” PV — 400 MWp with a 1,000 MWh battery

We build the external connection only: a 33/400 kV step-up substation with a 350 MVA transformer, the new 23.6 km “Gabare” 400 kV line and a new 400 kV bay at ESO’s “Mizia” substation. Design and construction of the external connection; equipment supply is in the client’s scope.

Isalnita · Romania · SolarPro

Our largest battery park — 158.6 MW / 634.4 MWh

A 33/110 kV step-up substation and battery park in Isalnita, Romania. Partial design and full construction works, on our own foundations made in Bulgaria and approved under Romanian legislation.

Krivodol · Bulgaria · Sustainable Energy Fund

Battery park 34.5 MW / 104.5 MWh

Connected to the transmission grid through a new 33/110 kV step-up substation, a 110 kV cable line and a new bay at an ESO 110 kV substation. Full EPC scope — from design to commissioning.

Full list

Reference list — completed projects.

Showing: 34 projects. Filter by category.

  1. 01

    “Tenevo Solar” — MV/400 kV substation, 400 kV switching station and reconstruction of the “San Stefano” 400 kV line

    Tenevo, Tundzha municipality, Yambol region
    Solarpro Technology AD
    Substations and switchyards
    21.03.2024 – 03.07.2025400 kV
  2. 02

    Burgas Energy Complex — BESS 150 MW / 601.7 MWh, 110/20 kV substation, 110 kV cable line

    Burgas
    Solarpro Technology AD
    Battery parks
    31.07.2025 – 13.02.2026150 MW / 601.7 MWh
  3. 03

    Smolyan Energy Complex — “Rozhen” 20/110 kV substation, 110 kV line, BESS 320 MWh

    Smolyan area
    Smolyan – VE EAD
    Substations and switchyards
    from 16.12.2024 — completed320 MWh
  4. 04

    New 400 kV overhead line — Lot 3, towers No. 288 – 427

    —
    Elektro-Konsortsium OOD
    Overhead and cable lines
    24.02.2020 – 22.12.2021400 kV
  5. 05

    “Vetrokom” battery storage — 65.55 MW / 154.77 MWh, connected to an operating wind farm

    —
    Solarpro Technology AD
    Battery parks
    10.12.2024 – 25.04.202565.55 MW / 154.77 MWh
  6. 06

    Reconstruction of the 110 kV switchyard at “Aldomirovtsi” 110/20 kV substation

    —
    ESO EAD
    Substations and switchyards
    07.07.2025 – 15.04.2026110 kV
  7. 07

    Rooftop PV 1,132 kWp + BESS 2,120 kWh, 40 Kuklensko Shose St.

    Plovdiv
    Krasin OOD
    PV + batteries
    3 months1,132 kWp / 2,120 kWh
  8. 08

    33 kV cable lines, internal roads and foundations for packaged transformer stations

    Tenevo, Yambol region
    Solarpro Technology AD
    Overhead and cable lines
    02.07.2024 – 02.06.202533 kV
  9. 09

    “Kameno” 33/110 kV step-up substation, 110 kV cable and line bay

    Kameno municipality, Burgas region
    Sunotec (with Futura Systems)
    Substations and switchyards
    07.04.2025 – 23.12.202533/110 kV
  10. 10

    “Brusartsi” 33/110 kV step-up substation and line bay in an ESO substation

    Brusartsi municipality, Montana region
    Sunotec (with Futura Systems)
    Substations and switchyards
    28.03.2025 – 23.12.202533/110 kV
  11. 11

    Reconstruction of the 110 kV switchyard at “Zlatograd” 110/20 kV substation

    —
    ESO EAD
    Substations and switchyards
    13.10.2025 – 19.05.2026110 kV
  12. 12

    PV 1,045 kWp + BESS 2,120 kWh

    Dimitrovgrad
    Simat AD
    PV + batteries
    2 months1,045 kWp / 2,120 kWh
  13. 13

    New control building at Plovdiv CHP

    Plovdiv
    ESO EAD
    Buildings and industrial
    29.04.2022 – 19.10.2022Building
  14. 14

    3 × 33 kV cable lines for PV grid connection

    Galabovo / Simeonovgrad municipalities
    Galabovo Solar BG EOOD
    Overhead and cable lines
    05.05.2023 – 01.08.202333 kV
  15. 15

    BESS 10 MW / 40 MWh, new 20 kV cable line and fibre-optic cable

    Kaliakra
    Kaliakra Storage System 3 EOOD
    Battery parks
    09.03.2026 – 05.08.202610 MW / 40 MWh
  16. 16

    Reconstruction of the 110 kV switchyard at “Iskar Industria” 110/20/6 kV substation

    —
    ESO EAD
    Substations and switchyards
    20.01.2023 – 09.01.2024110 kV
  17. 17

    Construction works for installation and grid connection of a BESS

    Enina, Kazanlak municipality
    Solarpro Technology AD
    Battery parks
    18.10.2024 – 25.04.2025BESS
  18. 18

    BESS 10 MW / 40 MWh, new 20 kV cable line and fibre-optic cable

    Kavarna
    Kavarna Energy System EOOD
    Battery parks
    09.03.2026 – 11.08.202610 MW / 40 MWh
  19. 19

    33 kV cable line to the 33/110 kV substation of the “Karlovo” PV plant

    Dabene, Karlovo municipality
    Karlovo Solar BG EOOD
    Overhead and cable lines
    24.11.2023 – 02.04.202433 kV
  20. 20

    Production centre, warehouse and office building — tanks / foundations stage

    Plovdiv
    BTL Industries AD
    Buildings and industrial
    10.02.2023 – 13.02.2024Industrial construction
  21. 21

    BESS 10 MW / 40 MWh, new 20 kV cable line and fibre-optic cable

    Trastikovo 1
    Trastikovo Storage System 1 EOOD
    Battery parks
    09.03.2026 – 14.08.202610 MW / 40 MWh
  22. 22

    BESS 10 MW / 40 MWh, new 20 kV cable line and fibre-optic cable

    Trastikovo 2
    Trastikovo Storage System 2 EOOD
    Battery parks
    09.03.2026 – 19.08.202610 MW / 40 MWh
  23. 23

    BESS 10 MW / 40 MWh, new 20 kV cable line and fibre-optic cable

    Staro Oryahovo
    Oryahovo Energy System EOOD
    Battery parks
    09.03.2026 – 22.08.202610 MW / 40 MWh
  24. 24

    BESS 10 MW / 40 MWh, new 20 kV cable line and fibre-optic cable

    Dalgopol — Storage Park
    Dalgopol Storage Park EOOD
    Battery parks
    09.03.2026 – 26.08.202610 MW / 40 MWh
  25. 25

    BESS 10 MW / 40 MWh, new 20 kV cable line and fibre-optic cable

    Dalgopol — Energy Park
    Dalgopol Energy Park EOOD
    Battery parks
    09.03.2026 – 29.08.202610 MW / 40 MWh
  26. 26

    Reconstruction of the “Obidim 1” 20 kV overhead line

    Blagoevgrad region
    ERM Zapad AD
    Overhead and cable lines
    25.05.2021 – 12.10.202120 kV
  27. 27

    20 kV switchgear and reconstruction of the 110 kV switchyard, “Mladost” substation

    —
    ERM Zapad AD
    Substations and switchyards
    20.11.2020 – 22.12.2021110 / 20 kV
  28. 28

    2 × transformer stations and connecting cable lines, “Hristo Botev” stadium

    Plovdiv
    Plovdiv Municipality
    LV networks and transformer stations
    16.03.2023 – 29.03.2023Transformer stations
  29. 29

    20/20 kV switchgear and telemechanics, “Dragalevtsi Farm”

    —
    ERM Zapad AD
    Substations and switchyards
    20.11.2020 – 14.12.202120 kV
  30. 30

    Reconstruction and new construction of LV overhead and cable networks

    Montana region
    ERM Zapad AD
    LV networks and transformer stations
    23.06.2021 – 23.12.2023LV
  31. 31

    Repair of 20 kV bays, “Hristo Smirnenski” substation

    —
    ESO EAD
    Substations and switchyards
    22.12.2021 – 07.07.202220 kV
  32. 32

    17.25 MW energy storage facility connected to the “Park Ramanusha” 110/33 kV substation

    —
    PSS Bulgaria OOD
    Battery parks
    04.03.2025 – 10.03.202517.25 MW
  33. 33

    Reconstruction and new construction of LV overhead and cable networks

    Razlog, Gotse Delchev, Sandanski, Petrich
    ERM Zapad AD
    LV networks and transformer stations
    27.07.2021 – 27.01.2024LV
  34. 34

    Internal 33 kV cable line, “Dabene” PV plant — stage 3

    Dabene
    Karlovo Solar BG EOOD
    Overhead and cable lines
    22.10.2024 – 15.12.202433 kV

Need a reference letter or a certificate of good performance?

Request the full dossier